Water Sector

Sl. No.

Name of scheme

Schematic amount (In Lakhs)

Implementing agency

Amount Released (In Lakhs)

Whether Plan & Estimate submitted

Progress of work

Remarks

1

Augmentation of 5 Nos. Existing water supply schemes

70.60

PHE, Dhemaji and Ghilamara Div.

Nil

Yes

No.

Action is being taken for release of 1st installment. File is under process.

2

Water Harvesting & Mini diversion weir 2 Nos.

10.00

D.O Soil Conservation, Silapather

6.00 L

Yes

As per report 60% works are in progress.

U/C was not yet submitted.

3

Installation of STW  

50.00

Executive Engg. Agril., Dhemaji

Nil

Plan & Estimate for an amount of Rs. 42.34 L is prepared for installation of 219  nos. STW and 375 Nos. of LLP for irrigation purpose.

Process for release of fund is being made & file is under process

 

4

Modernization existing irrigation scheme

40.00

Irrigation Department.

Nil

Not yet submitted

No

Irrigation department, Dhemaji is asked to submit P&E immediately

 

Total of Water Sector

170.60