Physical progress report on RSVY upto 25-03-08
(Rupees in Lac)
|
Sl No. |
Name of scheme |
Target for the year |
Unit |
Target for the quarter |
Cumulative achievement up to the end of the quarter |
Physical achievement (in %) |
Implementing agency |
Reasons of variance |
||||||||||
|
Total |
Target for ST |
Target for SC |
Total |
Target for ST |
Target for SC |
Total |
Achieve-ment for ST |
Achieve-ment for SC |
Total |
Achieve-ment for ST |
Achieve-ment for SC |
|||||||
|
1st phase |
2nd phase |
3rd phase |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
Agriculture Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
Vermi Compost |
15.00 |
4.00 |
- |
- |
- |
215nos |
215 nos. |
- |
- |
100% |
- |
- |
215 Nos. |
- |
- |
DAO, Dhemaji |
|
|
2 |
Multiple cropping
|
- |
41.04 |
33.00 |
- |
- |
628 Nos of SHG |
628 Nos of SHG |
- |
- |
100% |
- |
- |
628 Nos. of SHG |
- |
- |
-do- |
|
|
3 |
Horticulture plantation |
- |
- |
34.00 |
|
|
|
|
- |
- |
100% |
- |
- |
|
- |
- |
-do- |
|
|
4 |
Horticulture Nursery |
- |
- |
7.01 |
- |
- |
7Nos |
7 Nos |
- |
- |
100% |
- |
|
7 Nos. |
|
- |
-do- |
|
|
5 |
Motivation camp |
- |
- |
5.38 |
- |
- |
8Nos |
8Nos |
- |
- |
100% |
- |
- |
8 Nos. |
- |
- |
-do- |
|
|
6 |
Famers cum Tecnology Centre |
- |
- |
100.00 |
- |
- |
4Nos |
4Nos |
- |
- |
100% |
- |
- |
4 Nos. |
- |
- |
BDO Bordolani/Dhemaji/ Sissiborgaon/ Machkhuwa |
|
|
|
Agriculture Engineering Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7 |
Farm Mechanization, Distribution of Tractor & Power tiller at 33% Subsidy |
30.00 |
95.35 |
96.46 |
- |
- |
Tractor - 70 P. Tiller - 62 |
Tractor - 48 P. Tiller - 46 |
- |
- |
100% |
- |
- |
Tractor - 48 P. Tiller-46 |
- |
- |
E.E. Agriculture, Dhemaji |
|
|
|
Veterinary Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8 |
Pig Breeding unit |
20.26 |
56.49 |
|
- |
- |
107 unit + 298 unit |
405 nos. |
- |
- |
100% |
- |
- |
405 Nos. |
- |
- |
DVO, Dhemaji |
|
|
9 |
Revolving fund for developing piggery unit (250 Nos. X 12000/- per group) |
30.00 |
|
- |
- |
- |
41 Nos |
41 Nos |
- |
- |
20% |
- |
- |
41 Nos. |
- |
- |
D.V.O., Dhemaji |
The rest amount is allotted to new scheme due to non-viability |
|
10 |
Establishment of hatchery for promotion of poultry |
13.20 |
|
|
- |
- |
2 unit |
2 unit |
- |
- |
- |
- |
- |
- |
- |
- |
- |
The scheme is dropped due to non-viability |
|
11 |
Small pig breeding unit @ Rs. 12,000/- per unit. |
27.00 |
|
- |
- |
- |
42 nos. |
42 nos. |
- |
- |
25% |
- |
- |
42 Nos. |
- |
- |
D.V.O., Dhemaji |
The scheme is dropped due to non-viability |
|
12 |
Poultry units at 33% subsidy |
10.00 |
19.42 |
|
- |
- |
196 unit |
41 unit |
- |
- |
20% |
- |
- |
41 Nos. |
- |
- |
D.V.O, Dhemaji |
Regarding misutilisation of fund. Enquiry is going on. |
|
13 |
Goatery units |
- |
33.16 |
- |
- |
- |
254 nos. |
95 nos. |
- |
- |
40% |
|
|
95 Nos. |
|
|
-do- |
Regarding misutilisation of fund. Enquiry is going on. |
|
14 |
Mini slaughter house @ 1.15 lakh x 3 units (Bench Mark Survey) |
3.45
|
|
|
- |
- |
- |
- |
- |
- |
--- |
- |
- |
|
- |
- |
- |
Amount Utilized for Bench Mark Survey |
|
|
Fishery Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
Establishment of Eco Hatchery |
30.00 |
|
- |
- |
- |
4 unit |
4 unit |
- |
- |
100% |
- |
- |
4 unit |
- |
- |
DFDO, Dhemaji |
|
|
16 |
Fish seed rearing pond |
-
|
04.00 |
4.13 |
- |
- |
40 unit |
40 unit |
- |
- |
100% |
- |
- |
40 unit |
- |
- |
-do- |
|
|
17 |
Fishery in 0.1 Hector Pond. |
10.00
|
10.00 |
8.24 |
- |
- |
266 nos. Beneficiaries |
266 nos. Beneficiaries |
- |
- |
100% |
- |
- |
266 Nos. Beneficiaries |
- |
- |
-do- |
|
|
18 |
Development of derelict water bodies/ wet land etc. into fishery tank |
19.55 |
|
|
- |
- |
10 unit |
10 unit |
- |
- |
100% |
- |
- |
10 unit |
- |
- |
DFDO, Dhemaji |
|
|
|
Water Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
19 |
Augmentation of Existing water supply schemes |
70.60 |
- |
|
- |
- |
11 Nos. |
11 Nos. |
- |
- |
40% |
- |
- |
11Nos. scheme |
- |
- |
EE PHE, Ghilamara & Dhemaji |
The deptt. has misutilised the money abd bot completed the work . The complaint was lodged to Addl. Chief Secy , Assam Vide letter No. DD.32/DMJ/RSVY/2005-06/302 Dtd. 2-6-07 |
|
20 |
Water Harvesting & Mini diversion weir |
10.00 |
18.50 |
|
- |
- |
7 Nos. |
7 Nos. |
- |
- |
100% |
- |
- |
7 Nos. |
- |
- |
D.O Soil Conservation, Silapather |
|
|
21 |
Low Lift Points with diesel pump set |
- |
10.00 |
|
- |
- |
156 Nos. |
94 Nos. |
- |
- |
60% |
- |
- |
94 Nos. |
- |
- |
E.E, Agril, Dhemaji |
|
|
|
Sericulture and Hand loom Sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22 |
Eri Spinning machine at 33% subsidy |
5.00 |
|
|
- |
- |
303 Nos. beneficiaries |
21 Nos. |
- |
- |
5% |
- |
- |
21 Nos. beneficiaries |
- |
- |
Supdt. of Sericulture, Dhemaji |
Beneficiaries are demanding 50% subsidy. Hence the department has shown its inability to execute the scheme. |
|
23 |
Motorised Muga reeling machine at 33% subsidy |
5.00 |
|
|
- |
- |
126 Nos. beneficiaries |
19 Nos. |
- |
- |
10% |
- |
- |
19 Nos beneficiaries |
- |
- |
-do- |
Beneficiaries are demanding 50% subsidy. Hence the department has shown its inability to execute the scheme. |
|
24 |
Commercial Muga cocoon production through som plantation & silk warm rearing (243.8 Hect.) |
30.00 |
|
|
- |
- |
60 unit |
- |
- |
- |
Nil |
- |
- |
Nil |
- |
- |
- |
|
|
25 |
Establishment of Sericulture Nursery |
14.40 |
14.40 |
|
- |
- |
12 unit |
12 unit |
- |
- |
100% |
- |
- |
12 unit |
- |
- |
-do- |
|
|
26 |
Setting up of common facility center |
26.54 |
|
|
- |
- |
6 Nos. |
6 Nos. |
- |
- |
90% |
- |
- |
6 Nos |
- |
- |
Supdt.of Handloom &Textiles,Dhemaji |
|
|
27 |
Providing Dobby Jacquard looms to weavers through RSVY fund and bank loan |
10.00 |
|
|
- |
- |
158 Nos. beneficiaries |
- |
- |
- |
Nil |
- |
- |
Nil |
- |
- |
- |
The scheme is dropped due to non viability. |
|
28 |
Development of Handloom growth centre at Silapater |
- |
- |
20.00 |
- |
- |
1No. |
1No. |
- |
- |
75% |
|
|
|
|
|
BDO,Sissiborgaon |
|
|
29 |
Development of Handloom growth centre |
- |
- |
20.00 |
- |
- |
1No. |
1No. |
- |
- |
75% |
|
|
|
|
|
BDO,Bordolani |
|
|
30 |
Mirijeem Handloom Growth Center |
- |
- |
10.00 |
- |
- |
1 No. |
1No. |
- |
- |
80% |
|
|
|
|
|
BDO Dhemaji |
|
|
31 |
Construction of Common Facility Centre |
- |
- |
5.00 |
- |
- |
1No. |
1No. |
- |
- |
100% |
|
|
|
|
|
Supdt of Handloom & Texitle |
|
|
|
Infrastructure and other sector |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
32 |
Construction of Road |
100.00 |
|
|
- |
- |
4 Nos. roads |
4 Nos. roads |
- |
- |
95% |
- |
- |
4 nos. roads |
- |
- |
Ex –Engineer PWD (Rural) Road, silapather. |
|
|
33 |
Construction of RCC bridge No.5/1,7/1 and 8/1 on Khalihamari Butikur Road |
- |
- |
5,31,51,705.00 |
- |
- |
3 Nos bridges and 1 No. road |
3 Nos. bridges and 1 No. road |
|
|
20% |
- |
- |
3 nos bridge and road |
- |
- |
Executive Engineer PWD (State) Road |
|
|
34 |
Const of Road from Dhemaji Chariali to Dusutimukh |
- |
- |
34,15,896.00 |
- |
- |
1 No. road |
1 No. road |
- |
- |
57% |
- |
- |
1 nos road |
- |
- |
Executive Engineer PWD (State) Road |
|
|
35 |
Con and Repairing of Road from Gogamukh to Ghilamara |
- |
- |
1,14,44,459.00 |
- |
- |
1 No. road |
1 No. road |
|
|
30% |
|
|
1 nos road |
|
|
Executive Engineer PWD (State) Road |
|
|
36 |
Provision of Electricity |
30.00 |
|
|
- |
- |
Installation of transformer (11 KV, LT line and sub-station of 4 nos. villages. |
Installation of transformer (11 KV, LT line and sub-station of 4 nos. villages. |
- |
- |
100% |
- |
- |
4 Nos. villages. |
- |
- |
Executive Engineer, ASEB, Dhemaji |
|
|
37 |
Provision of Electricity |
- |
2,89,076 |
|
|
|
Installation of transformer (11 KV) Line Gogamukh PHC |
- |
- |
- |
90% |
- |
|
1Nos |
- |
|
Executive Engineer, ASEB, Dhemaji |
|
|
38 |
Construction of Tourism complex |
40.00 |
80.00 |
|
- |
- |
3 Nos. |
3 Nos. |
- |
- |
80% |
- |
- |
3 Nos |
- |
- |
Executive Engg. PWD (Bldn.)&PD DRDA Dhemaji. |
|
|
39 |
Construction of SHG Hat
|
50.00 |
50.00 |
50.00 |
- |
- |
18 Nos. |
18 Nos. |
- |
- |
100% |
- |
- |
18 Nos |
- |
- |
Executive Engg. PWD (Bldn.) |
|
|
40 |
Construction of Rural Market Shed |
50.00 |
- |
- |
- |
- |
16 Nos. |
- |
- |
- |
80 % |
- |
- |
16 Nos |
- |
- |
-do- |
|
|
41 |
Construction of Girl’s Hostel at Dhemaji College |
30.00 |
- |
- |
- |
- |
1 No |
- |
- |
- |
83% |
- |
- |
1 Nos |
- |
- |
P.D. DRDA,Dhemaji |
|
|
42 |
Construction of Children’s Educational & Career Development Centre |
|
500.00 |
-- |
-- |
-- |
1 No. |
1 No. |
|
-- |
-- |
-- |
-- |
-- |
-- |
-- |
|
|
|
Sports And Youth Welfare |
||||||||||||||||||
43 |
Development ofParade Ground |
-- |
-- |
20.00 |
- |
-- |
1 No. |
1 No. |
|
|
75% |
|
|
1 No. |
|
|
P.D. DRDA,Dhemaji |
|
44 |
Renovation ofStadium |
- |
- |
10.00 |
- |
- |
1 No. |
1 No. |
|
|
80% |
|
|
1 No. |
|
|
AEE, PWD( B) Dhemaji |
|
|
Transport Sector |
||||||||||||||||||
45 |
Bus Stand |
- |
- |
20.00 |
- |
- |
4 Nos. |
4 Nos. |
|
|
100% |
|
|
4 Nos. |
|
|
SDO(C) Jonai, AEE PWD (B), BDO ,Bordoloni |
|
|
Cultural Affairs |
||||||||||||||||||
46 |
ConstructionSukafa Bhawan |
_ |
_ |
10.00 |
_ |
_ |
1No. |
1 No. |
|
|
80% |
|
|
1 No. |
|
|
BDO, Dhemaji |
|
|
|
Grand Total |
|
|
1500.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Deputy Commissioner,
Dhemaji